Georgian Trail Pedestrian Bridge


Introduction:

This project will replace Structure 125, a pedestrian bridge on the Georgian Trail just north of Edwin Street, where the trail crosses Meaford Creek. The goal of the project is to improve safety and provide a durable, long-term crossing for trail users.

Project Description:

This project includes: 

  • Completing a Schedule B Municipal Class Environmental Assessment including a review of design alternatives 
  • Removing the existing bridge, if required as part of the final design 
  • Construction of the preferred solution identified through the Class EA process 
  • Making trail adjustments and restoring the surrounding area once construction is complete 

Status: In Progress

Contact:

Phases:

November 30, 2026

Anticipated Completion: November 2026 

October 31, 2026

Anticipated Construction: September – October 2026 

June 20, 2026

Engineering and Design: Winter – Spring 2026 

Budget:

Total budget of $368,000

Additional Resources:

additional-resources
  • Heritage Impact Assessment
  • Cultural Heritage Evaluation Report
  • Notice of Study Commencement and Public Information Centre
  • Community Information Session Presentation