7th Line Bridge Replacement


Introduction:

The Municipality of Meaford is replacing the bridge on 7th Line (Structure BR-069) to ensure the road remains safe and reliable. This work involves removing the old concrete bridge and installing a new concrete structure in its place. 

Project Description:

This project includes: 

  • Removing the existing concrete bridge 
  • Installing a new concrete structure 
  • Work is carried out by Cox Construction Limited 

Additional Information:

Impact on Residents 

Traffic Disruptions:  

  • 7th Line is closed at the bridge for the duration of construction. 
  • Please use alternate routes for through traffic. 
  • Residents can still access their properties, but do not park on the roadway. 

Noise and Dust:Shape Some noise and dusty conditions are expected during construction. 

Status: Complete

Contact:

Phases:

October 31, 2025

Anticipated ongoing end: October 31, 2025

September 8, 2025

Anticipated project start: September 8, 2025

Budget:

Total Budget: $753,095 